Client : African Clean Energy Developments (ACED) 
Contract Value : R 318 million. 

Adenco Construction was the electrical contractor on Castle Wind Farm a 89 MW, 16 tower wind farm located near De Aar , Northern Cape South Africa.

Adenco completed all the external electrical connections to the 16 wind turbine generators; the IPP Step Up Substations; Eskom Substations and 132kV Overhead Transmission line.

The EBOP works comprised of the following:

  • 66km of underground 33kV Cable Network
  • 26km of 132kV Overhead Line
  • Construction of 132/33kV IPP Substation
  • Construction of 132kV Eskom Moyeng Substation
  • Bay extension at existing Eskom 132kV Hydra Substation